|
April 5, 2001
To: The Campus Community
From: Transportation and Parking Services
Re: Mission Street construction update
Caltrans has alerted the campus that construction in the middle of the Bay/Mission
intersection is scheduled to begin Monday, April 9, and may last through Thursday,
April 12. While this work is underway, southbound Bay Street traffic will be required
to turn left or right onto Mission--traffic will not be allowed to continue south
through the intersection (toward the Wharf). Similarly, SCMTD's Route 1B Lower Bay
buses will detour onto Mission Street before continuing south along Bay from California
toward West Cliff Drive. "Road Construction Ahead" signs will be posted
along Bay Street at King Street (southbound) and at Seaside (northbound) to warn
traffic of the construction work.
Commuters should call the Mission Street Widening Project's 24-hour information hotline
(420-6242) for up-to-the-hour status reports on construction delays and detours.
Please remember that all work is weather dependent.
This work is necessary to connect a new 14-inch water main into the existing city
water system and has been scheduled to coincide with the Spring Break at Bayview
Elementary School. If all goes smoothly, this work may be completed in only two
days instead of the scheduled four. Similar work conducted along Mission Street since
December has allowed water and storm drain systems to be installed or renovated prior
to the next phase of the Mission Street Widening project.
Stage 2 of the Mission Street Widening Project is scheduled to begin in early May
and will affect the roadway between Otis and Bay streets. Work will proceed on the
northbound side of Mission through July, then shift to the southbound side. Current
plans indicate that Stage 2 will be completed in August. Construction along this
section of Mission is likely to have the greatest impact on University-related traffic--including
the SCMTD bus routes along Laurel and Walnut streets. Fortunately, Caltran's efforts
to schedule this work during the late spring and summer--and complete it before the
start of Fall Quarter--should help reduce impacts on the campus and local community.
For more information, visit the Mission
Street Widening Project website: (http://www.missionwidening.com - no longer active. 12/02).
|